MasterFormat Division 00 vs Division 01

Compare procurement and contracting documents with general requirements, and see where to find each in the project manual.

Quick answer

MasterFormat Division 00 organizes procurement and contracting documents, including bidding instructions, bid forms, agreements, and conditions of the contract. Division 01 organizes project-wide requirements in the specifications, such as submittal procedures, temporary facilities, quality procedures, and closeout. Use Division 00 to find how the project is procured and contracted. Use Division 01 to find common requirements for carrying out the work.

Expanded Concrete hierarchy with MasterFormat 2026 Edition and 26.1 OIR selected
The Concrete division expanded in CDS with MasterFormat 2026 and OIR 26.1 selected.

Where to look in the project manual

  • How do we submit a bid? Start with Division 00 for the instructions and bid form. Confirm which addenda apply and whether the owner requires any attachments with the bid.
  • How do we administer submittals, meetings, or temporary facilities? Start with Division 01 for the procedures that apply across the project. Check the relevant technical section for the deliverables and acceptance requirements for that work.
  • Which alternates became part of the contract? Read the executed agreement and other documents incorporated into the contract. Review the applicable specifications and drawings for the scope and how to carry it out.

Example: an alternate floor finish

The owner requests a price for a different floor finish. The estimator starts with the Division 00 instructions and bid form to find how the price should be entered and what information is due with the bid. Then the estimator reads the drawings and applicable specification sections to determine which rooms are affected, whether preparation changes, and what materials or installation are included in the alternate.

After award, the project manager checks the agreement and incorporated documents to confirm whether the owner accepted the alternate. The manager reviews Division 01 for the project-wide submittal procedure and uses the finish specification to identify the required samples, product data, and installation criteria. The bid form, project-wide procedure, and finish requirements each answer a different question about the same work.

Where requirements overlap

A project may address timing, pricing, substitutions, or closeout in several documents. For example, a bid substitution deadline may appear in the instructions to bidders, while a procedure for considering a substitution during construction may be in Division 01. Read each requirement in the context of when it applies and which document governs that decision.

Keep a record of the document, section, and revision you checked. If the requirements conflict or leave responsibility unclear, follow the project’s clarification procedure and consult its provisions for resolving document conflicts. The MasterFormat division number helps locate information. The project documents determine the applicable requirements.

Check the handoff from bidding to construction

A bid instruction may ask for an alternate price as an addition to the base bid. When the alternate is accepted, confirm that the procurement record, the executed agreement, and the construction team’s scope list identify the same option. If the bid form and drawings name it differently, keep both references and resolve the difference before issuing purchase orders.

Verify the classification in CSI Dynamic Standards

Use the MasterFormat overview to learn how numbered divisions and sections organize project information. In [CSI Dynamic Standards](https://standards.theconstructionstandard.com/web/search-tree), choose the MasterFormat edition for the project and open Division 00 or 01. Compare the number and title with your project manual and use the manual itself to find the project-specific text. Sign up for access or review pricing to choose access for your team.

Access Current CSI Standards

CSI Dynamic Standards provides authorized access to MasterFormat, UniFormat, and OmniClass through a connected, edition-aware platform. Create an account to view access options, or review pricing for organization-wide standards use.

Sources and review scope

Reviewed against CSI’s public standards information for scope, terminology, and licensing context. This public guide provides orientation and does not reproduce or replace the licensed standard. Content review date: November 11, 2026.

COMMON QUESTIONS
General and supplementary conditions are contracting documents organized under Division 00. Division 01 contains general requirements in the specifications.
Check Division 01 for project-wide submittal procedures and the applicable technical section for the submittals required for that work.